PMP · Question 80 · Task 2: Evaluate and deliver project benefits and value
A project manager is working on a project where the client has requested a feature that would provide significant business value but would require the team to learn a new technology. The learning curve would add 3 weeks to the project timeline. What should the project manager do?
Answer options:
Recommend against the feature due to the timeline impact and learning curve
Present the client with a clear analysis of the business value, learning requirements, timeline impact, and long-term benefits
Implement the feature using existing technology to avoid the learning curve
Propose hiring external experts to implement the feature with the new technology