Hard1 markMultiple Choice
Task 9: Integrate project planning activitiestechnical decision makingarchitectural choicesstructured evaluationdecision criteria

PMP · Question 57 · Task 9: Integrate project planning activities

A project manager is leading a team where two senior developers have fundamentally different approaches to solving a critical technical problem. Both approaches are technically sound but would lead to different system architectures. The decision needs to be made soon to avoid project delays. What should the project manager do?

Answer options:

A.

Choose the approach from the more experienced developer

B.

Ask the developers to compromise and combine elements from both approaches

C.

Facilitate a structured decision-making process that evaluates both approaches against project criteria and constraints

D.

Escalate the decision to the technical architect or senior management

How to approach this question

When facing technical decisions with multiple valid options, use structured evaluation against project criteria rather than relying on authority or compromise.

Full Answer

C.Facilitate a structured decision-making process that evaluates both approaches against project criteria and constraints✓ Correct
Structured decision-making using project criteria ensures technical decisions align with project objectives and constraints rather than personal preferences.

Common mistakes

Relying on authority, forcing compromise, or escalating without first attempting structured evaluation of the options.

Practice the full PMI PMP Practice Exam 3

100 questions · hints · full answers · grading

More questions from this exam