Hard1 markMultiple Choice
Task 10: Manage project changeschange implementationrework managementimplementation planningchange control

PMP · Question 39 · Task 10: Manage project changes

A project manager is working on a predictive project where a major scope change has been approved by the change control board. The change will add 4 weeks to the schedule and $50,000 to the budget. However, implementing the change will require rework of already completed deliverables. What should the project manager do FIRST?

Answer options:

A.

Begin implementing the change immediately since it has been approved

B.

Develop a detailed implementation plan that minimizes rework and optimizes the integration of changes

C.

Communicate the change to all stakeholders and update project documentation

D.

Assess whether the approved change is still the best option given the rework requirements

How to approach this question

Even approved changes require careful implementation planning, especially when they involve rework of completed work.

Full Answer

B.Develop a detailed implementation plan that minimizes rework and optimizes the integration of changes✓ Correct
Approved changes involving rework require careful implementation planning to minimize disruption and optimize the integration of new requirements.

Common mistakes

Assuming that approved changes can be implemented immediately without planning, especially when rework is involved.

Practice the full PMI PMP Practice Exam 3

100 questions · hints · full answers · grading

More questions from this exam