For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 3Question 33
    Hard1 markMultiple Choice
    Task 17: Plan and manage project/phase closure or transitionsproject closurelessons learnedknowledge transferteam transition

    PMP · Question 33 · Task 17: Plan and manage project/phase closure or transitions

    A project manager is planning the closure of a successful project. The project deliverables have been accepted, but there are several lessons learned that could benefit future projects. The team is eager to move on to new assignments. Which TWO actions should the project manager prioritize during project closure?

    Answer options:

    A.

    Conduct an extensive post-project review with all stakeholders

    B.

    Capture and document key lessons learned while team knowledge is still fresh

    C.

    Celebrate project success with the team before they disperse

    D.

    Ensure proper knowledge transfer to operations or maintenance teams

    E.

    Complete all administrative closure activities like contract closeouts

    F.

    Archive all project documentation for future reference

    How to approach this question

    Focus on closure activities that require team availability and fresh knowledge - lessons learned capture and knowledge transfer are time-sensitive.

    Full Answer

    Lessons learned capture (B) and knowledge transfer (D) are most effective when done while team knowledge is fresh and members are available.

    Common mistakes

    Prioritizing administrative tasks or celebrations over knowledge-based activities that become much more difficult once the team disperses.
    Question 32All questionsQuestion 34

    Practice the full PMI PMP Practice Exam 3

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two team members engage in a heated argument a...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn, is frequently ...HardQ04During sprint planning for a software development project, the development team reports that they...HardQ05A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completio...Hard
    View all 100 questions →