    Hard1 markMultiple Choice
    Task 1: Manage conflictstakeholder managementteam protectionconflict de-escalationprofessional communication

    PMP · Question 31 · Task 1: Manage conflict

    During a project review meeting, a senior stakeholder criticizes the project team's performance in front of other stakeholders, causing visible distress to team members. The criticism is partially valid but delivered inappropriately. What should the project manager do FIRST?

    Answer options:

    A.

    Defend the team immediately and redirect the conversation to project accomplishments

    B.

    Acknowledge the concerns professionally and suggest discussing specific improvement actions privately after the meeting

    C.

    Ask the stakeholder to provide specific examples and evidence for their criticism

    D.

    End the meeting immediately to prevent further damage to team morale

    How to approach this question

    Balance protecting team morale with addressing valid concerns. Look for approaches that de-escalate while moving toward constructive resolution.

    Full Answer

    B.Acknowledge the concerns professionally and suggest discussing specific improvement actions privately after the meeting✓ Correct
    Effective leadership acknowledges valid concerns while protecting team morale and redirecting toward constructive problem-solving in appropriate settings.

    Common mistakes

    Either completely defending the team (ignoring valid concerns) or allowing public criticism to continue (damaging team morale).
    Question 30All questionsQuestion 32

    Practice the full PMI PMP Practice Exam 3

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two team members engage in a heated argument a...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn, is frequently ...HardQ04During sprint planning for a software development project, the development team reports that they...HardQ05A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completio...Hard
    View all 100 questions →