For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 3Question 15
    Hard1 markMultiple Choice
    Task 3: Evaluate and address external business environment changes for impact on scoperegulatory changesexternal environmentimpact assessmenthybrid methodology

    PMP · Question 15 · Task 3: Evaluate and address external business environment changes for impact on scope

    A software project team is using a hybrid approach where requirements are defined upfront but development occurs in two-week iterations. During the third iteration, new regulatory requirements emerge that affect the core functionality. What should the project manager do FIRST?

    Answer options:

    A.

    Continue with the current iteration and address regulatory requirements in the next iteration

    B.

    Immediately stop all development work until the regulatory requirements are fully analyzed

    C.

    Assess the impact of the regulatory changes on current and planned work, then adjust the approach accordingly

    D.

    Escalate to the sponsor to decide whether to continue with the original requirements or adopt the new regulations

    How to approach this question

    Regulatory changes require immediate assessment but measured response. Determine impact before making decisions about work continuation or stoppage.

    Full Answer

    C.Assess the impact of the regulatory changes on current and planned work, then adjust the approach accordingly✓ Correct
    External regulatory changes require immediate assessment to understand their impact on current and planned work before determining the appropriate response.

    Common mistakes

    Either ignoring regulatory changes by continuing current work, or overreacting by stopping all work without assessment.
    Question 14All questionsQuestion 16

    Practice the full PMI PMP Practice Exam 3

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two team members engage in a heated argument a...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn, is frequently ...HardQ04During sprint planning for a software development project, the development team reports that they...HardQ05A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completio...Hard
    View all 100 questions →