Hard1 markShort Answer

PMP · Question 19 · Task 5: Plan and manage budget and resources

A project has a Budget at Completion (BAC) of $200,000. The project is 50% complete. The Actual Cost (AC) is $120,000. The Earned Value (EV) is $100,000. The project manager expects the current cost variance to continue. What is the Estimate at Completion (EAC)? (Enter the number only, no currency symbols)

How to approach this question

Calculate CPI, then use EAC = BAC / CPI.

Full Answer

CPI = 100,000 / 120,000 = 0.8333. EAC = 200,000 / 0.8333 = 240,000.

Common mistakes

Using the wrong EAC formula (e.g., AC + ETC) when the variance is expected to continue.

Practice the full PMI PMP Mini Practice Exam 3

20 questions · hints · full answers · grading

More questions from this exam