Hard1 markMultiple Choice
PMP · Question 18 · Task 4: Engage stakeholders
You are managing a project with a large, diverse group of stakeholders. You have classified them using a Power/Interest grid. A group of community activists has high interest but low power. However, they are very vocal on social media. How should you engage them?
You are managing a project with a large, diverse group of stakeholders. You have classified them using a Power/Interest grid. A group of community activists has high interest but low power. However, they are very vocal on social media. How should you engage them?
Answer options:
A.
Monitor them only, as they have low power.
B.
Keep them informed and manage their expectations proactively to prevent negative sentiment.
C.
Manage them closely as key decision-makers.
D.
Invite them to the project board meetings.
How to approach this question
Apply the Power/Interest grid strategy but adjust for the 'vocal' context.
Full Answer
B.Keep them informed and manage their expectations proactively to prevent negative sentiment.✓ Correct
While traditionally 'Keep Informed', the social media aspect suggests they could impact the project's reputation, so proactive communication is vital.
Common mistakes
Underestimating them (A) or Overestimating them (C).
Practice the full PMI PMP Mini Practice Exam 3
20 questions · hints · full answers · grading
More questions from this exam
Q1A project manager is leading a hybrid project with a distributed team. During a virtual sprint re...HardQ2A project manager has just taken over a project where the team morale is low. The previous PM was...HardQ3A high-performing team member in an agile project has recently started missing deadlines and with...HardQ4A project manager is leading a cross-functional team where decision-making has been slow because ...HardQ5A project team is transitioning from predictive to agile. During the first sprint, the PM notices...Hard
Expert