PMP · Question 20 · Task 6: Plan and manage schedule
A project is using a hybrid approach. The hardware components follow a predictive schedule, while software is agile. The hardware delivery is delayed by 2 weeks due to supply chain issues. This hardware is required for the software team's integration testing in the current sprint. What should the PM do?
Answer options:
Pause the software sprint until the hardware arrives.
Force the hardware vendor to expedite delivery.
Work with the Product Owner to reprioritize the backlog, moving integration stories to a future sprint and pulling in other work.
Extend the sprint duration by 2 weeks.