PMP · Question 52 · Task 15: Manage project issues
A major dispute arises between two key vendors regarding the integration of their subsystems. The project is stalling. What is the BEST way for the project manager to resolve this issue?
Answer options:
Terminate one of the contracts.
Ask the legal department to sue both vendors.
Facilitate a collaborative problem-solving session with both vendors to find a technical solution.
Decide on the technical solution yourself and order them to implement it.