Hard1 markMultiple Choice
PMP · Question 51 · Task 14: Establish project governance structure
An agile team wants to skip the daily stand-up because they feel it is a waste of time. How should the project manager (acting as Scrum Master) respond?
An agile team wants to skip the daily stand-up because they feel it is a waste of time. How should the project manager (acting as Scrum Master) respond?
Answer options:
A.
Allow them to skip it; they are self-organizing.
B.
Force them to attend and take attendance.
C.
Change it to a weekly meeting.
D.
Explore why they feel it is a waste and help them improve the meeting's value while maintaining the practice.
How to approach this question
Balance 'Rules' (Governance) with 'Coaching' (Agile).
Full Answer
D.Explore why they feel it is a waste and help them improve the meeting's value while maintaining the practice.✓ Correct
Task 14 involves determining appropriate governance. In Scrum, the events are mandatory governance elements. The PM's role is to ensure they are valuable, not to remove them.
Common mistakes
Misinterpreting 'self-organization' as 'do whatever you want' (A).
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
Expert