Hard1 markMultiple Choice
Task 12: Manage project artifactsTask 12ArtifactsDefinitions

PMP · Question 43 · Task 12: Manage project artifacts

Which plan defines how versioning of project documents and deliverables will be managed?

Answer options:

A.

Quality Management Plan

B.

Configuration Management Plan

C.

Change Management Plan

D.

Scope Management Plan

How to approach this question

Match 'Versioning' to 'Configuration'.

Full Answer

B.Configuration Management Plan✓ Correct
Task 12. Configuration Management ensures that everyone is working on the correct version of a document or product component.

Common mistakes

Confusing Change Management (Process of approval) with Configuration Management (State/Version control).