Hard1 markMultiple Choice
PMP · Question 43 · Task 12: Manage project artifacts
Which plan defines how versioning of project documents and deliverables will be managed?
Which plan defines how versioning of project documents and deliverables will be managed?
Answer options:
A.
Quality Management Plan
B.
Configuration Management Plan
C.
Change Management Plan
D.
Scope Management Plan
How to approach this question
Match 'Versioning' to 'Configuration'.
Full Answer
B.Configuration Management Plan✓ Correct
Task 12. Configuration Management ensures that everyone is working on the correct version of a document or product component.
Common mistakes
Confusing Change Management (Process of approval) with Configuration Management (State/Version control).
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
Expert