PMP · Question 18 · Task 5: Plan and manage budget and resources
An agile project has a fixed budget but variable scope. The sponsor wants to know how the team tracks if they are on budget. Which metric is MOST appropriate for the project manager to present?
Answer options:
Schedule Performance Index (SPI)
Estimate to Complete (ETC)
Velocity
Cost Performance Index (CPI) or Burn rate