For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMP Process Domain Practice ExamQuestion 17
    Hard1 markMultiple Choice
    Task 5: Plan and manage budget and resourcesTask 5BudgetReserves

    PMP · Question 17 · Task 5: Plan and manage budget and resources

    A project manager discovers a major design flaw that was not identified in the risk register. Fixing it requires $50,000. The project has $20,000 in Contingency Reserves and $60,000 in Management Reserves. How should the project manager fund this fix?

    Answer options:

    A.

    Use the Contingency Reserve.

    B.

    Use the Management Reserve immediately.

    C.

    Submit a change request to use the Management Reserve.

    D.

    Ask the sponsor for additional funding outside the project budget.

    How to approach this question

    Identify the type of risk (unidentified) -> Management Reserve. Identify the process -> Change Request.

    Full Answer

    C.Submit a change request to use the Management Reserve.✓ Correct
    Contingency = Identified Risks. Management = Unidentified Risks. Moving money from Management Reserve to the Baseline always requires a Change Request.

    Common mistakes

    Using Contingency for unidentified risks, or spending Management Reserve without approval.
    Question 16All questionsQuestion 18

    Practice the full PMP Process Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
    View all 60 questions →