PMP · Question 17 · Task 5: Plan and manage budget and resources
A project manager discovers a major design flaw that was not identified in the risk register. Fixing it requires $50,000. The project has $20,000 in Contingency Reserves and $60,000 in Management Reserves. How should the project manager fund this fix?
Answer options:
Use the Contingency Reserve.
Use the Management Reserve immediately.
Submit a change request to use the Management Reserve.
Ask the sponsor for additional funding outside the project budget.
60 questions · hints · full answers · grading