Hard1 markMultiple Choice
PMP · Question 56 · Task 13: Mentor relevant stakeholders
A new team member is highly experienced technically but struggles with the organization's complex political landscape. The PM is new to the organization as well. What is the BEST mentoring approach?
A new team member is highly experienced technically but struggles with the organization's complex political landscape. The PM is new to the organization as well. What is the BEST mentoring approach?
Answer options:
A.
Mentor the team member yourself on politics.
B.
Connect the team member with a long-tenured senior colleague who can act as a mentor.
C.
Tell the team member to ignore politics and focus on code.
D.
Send the team member to a generic negotiation class.
How to approach this question
If you (the PM) lack the skill/knowledge, find someone who has it.
Full Answer
B.Connect the team member with a long-tenured senior colleague who can act as a mentor.✓ Correct
A key part of Task 13 is 'Allocate time for mentoring' and connecting people. If the PM cannot mentor (due to lack of knowledge), they should facilitate a relationship with someone who can.
Common mistakes
Thinking the PM must be the expert on everything (A).
Practice the full PMP People Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard
Expert