    PracticePMI PMP®PMP People Domain Practice ExamQuestion 13
    Hard1 markMultiple Choice
    Task 3: Support team performanceTeam PerformanceMentoring

    PMP · Question 13 · Task 3: Support team performance

    A project manager wants to support the growth of a high-potential team member who aspires to a leadership role. Which TWO actions are most appropriate?

    Answer options:

    A.

    Assign the team member all the administrative tasks to test their patience.

    B.

    Delegate a small, low-risk sub-project for them to lead, providing coaching as needed.

    C.

    Invite the team member to shadow the PM during stakeholder negotiation meetings.

    D.

    Send the team member to a generic leadership seminar without follow-up.

    E.

    Promote them immediately to lead the team.

    How to approach this question

    Select actions that involve active learning (doing/seeing) with support.

    Full Answer

    Development is best achieved through a mix of experience (70%), exposure (20%), and education (10%). Delegating a sub-project and shadowing cover the experience and exposure aspects effectively.

    Common mistakes

    Relying solely on formal training (D).
    Question 12All questionsQuestion 14

    Practice the full PMP People Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard
    View all 60 questions →