Hard1 markMultiple Choice
PMP · Question 07 · Task 2: Lead a team
A team is comprised of junior members who are enthusiastic but lack experience. The project has a strict regulatory deadline. Which leadership approach is MOST appropriate initially?
A team is comprised of junior members who are enthusiastic but lack experience. The project has a strict regulatory deadline. Which leadership approach is MOST appropriate initially?
Answer options:
A.
Delegating
B.
Supporting
C.
Directing
D.
Coaching
How to approach this question
Apply Situational Leadership theory. Match the team's maturity (Low Competence, High Commitment) to the style.
Full Answer
C.Directing✓ Correct
While agile favors servant leadership, situational leadership dictates that inexperienced teams under tight constraints initially need directive leadership to understand tasks and standards before they can be empowered.
Common mistakes
Assuming 'Directing' is always wrong in PMP. It is valid for specific contexts (safety, junior teams, crisis).
Practice the full PMP People Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard