Hard1 markMultiple Choice
Task 4: Support organizational changeBusiness EnvironmentOrg ChangeTask 4

PMP · Question 57 · Task 4: Support organizational change

Who is ULTIMATELY responsible for championing the organizational change brought about by the project and removing high-level political roadblocks?

Answer options:

A.

The Project Manager

B.

The Project Sponsor

C.

The Project Team

D.

The Functional Manager

How to approach this question

Sponsor = Champion/Political Cover/Money.

Full Answer

B.The Project Sponsor✓ Correct
While the PM supports change, the Project Sponsor is accountable for enabling the change at the executive level and removing political barriers.

Common mistakes

Thinking the PM has to do everything. The PM escalates political blocks to the Sponsor.

Practice the full PMP Business Environment Domain Practice Exam

60 questions · hints · full answers · grading

More questions from this exam