    PracticePMI PMP®PMP Business Environment Domain Practice ExamQuestion 49
    Hard1 markMultiple Choice
    Task 4: Support organizational changeBusiness EnvironmentOrg ChangeTask 4

    PMP · Question 49 · Task 4: Support organizational change

    An organization is undergoing a merger during the project. As a result, key subject matter experts (SMEs) assigned to the project are feeling insecure about their jobs and productivity has dropped.<br/><br/>What should the project manager do?

    Answer options:

    A.

    Tell the team to focus on work and ignore the rumors.

    B.

    Facilitate an open discussion to address concerns and advocate for the team's stability with leadership.

    C.

    Replace the distracted SMEs with contractors.

    D.

    Pause the project until the merger is complete.

    How to approach this question

    Org Change Impact on Team -> Support/Facilitate/Advocate.

    Full Answer

    B.Facilitate an open discussion to address concerns and advocate for the team's stability with leadership.✓ Correct
    Organizational changes (mergers) impact project resources emotionally. The PM must support the team (Task 4) by facilitating communication and advocating for them. Ignoring feelings (A) leads to failure.

    Common mistakes

    Focusing only on tasks (A) and ignoring the human element of change.
    Question 48All questionsQuestion 50

    Practice the full PMP Business Environment Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard
    View all 60 questions →