    PracticePMI PMP®PMP Business Environment Domain Practice ExamQuestion 46
    Hard1 markMultiple Choice
    Task 4: Support organizational changeBusiness EnvironmentOrg ChangeTask 4

    PMP · Question 46 · Task 4: Support organizational change

    A project manager is assessing the organizational culture before launching a major change initiative. The organization is highly hierarchical, decisions are made only by senior leadership, and strict adherence to rules is expected.<br/><br/>Which type of culture is this?

    Answer options:

    A.

    Power/Role Culture

    B.

    Task Culture

    C.

    Person Culture

    D.

    Agile Culture

    How to approach this question

    Match the description to the Culture Type. Hierarchy/Rules = Role/Power.

    Full Answer

    A.Power/Role Culture✓ Correct
    Understanding organizational culture is key to Task 4. A hierarchy with strict rules and centralized power is a Power or Role culture. The PM must adapt their change strategy to respect this hierarchy (e.g., get top-down buy-in).

    Common mistakes

    Confusing with Task culture (which is about the work, not the rank).
    Question 45All questionsQuestion 47

    Practice the full PMP Business Environment Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard
    View all 60 questions →