PMP · Question 41 · Task 3: Evaluate and address external business environment changes
How frequently should a project manager review the external business environment for impacts on the project scope?
Answer options:
Only during the initiation phase.
Only when a risk is triggered.
Continually throughout the project lifecycle.
Only at the end of each phase.