Hard1 markMultiple Choice
Task 3: Evaluate and address external business environment changesBusiness EnvironmentExternal EnvironmentTask 3Agile
PMP · Question 36 · Task 3: Evaluate and address external business environment changes
An Agile team is building a financial app. A new 'Open Banking' standard is released by the industry regulator. The Product Owner decides to adopt this standard immediately to gain a competitive advantage, even though it wasn't mandatory yet.<br/><br/>How does this external change impact the project scope/backlog?
An Agile team is building a financial app. A new 'Open Banking' standard is released by the industry regulator. The Product Owner decides to adopt this standard immediately to gain a competitive advantage, even though it wasn't mandatory yet.<br/><br/>How does this external change impact the project scope/backlog?
Answer options:
A.
It has no impact as the standard is not mandatory.
B.
New user stories must be added to the backlog and prioritized against existing work.
C.
The project must be paused to rewrite the charter.
D.
The team must work overtime to include the new standard without affecting the schedule.
How to approach this question
External Opportunity -> PO Decision -> Backlog Update.
Full Answer
B.New user stories must be added to the backlog and prioritized against existing work.✓ Correct
External changes can be opportunities. If the PO decides to pursue it, the scope (Backlog) changes. New stories are added and prioritized. Agile teams do not just add work on top (D); they trade off priorities.
Common mistakes
Thinking 'not mandatory' means 'ignore' (A), ignoring the PO's decision.
Practice the full PMP Business Environment Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard
Expert