Hard1 markMultiple Choice
Task 3: Evaluate and address external business environment changesBusiness EnvironmentExternal EnvironmentTask 3Agile

PMP · Question 36 · Task 3: Evaluate and address external business environment changes

An Agile team is building a financial app. A new 'Open Banking' standard is released by the industry regulator. The Product Owner decides to adopt this standard immediately to gain a competitive advantage, even though it wasn't mandatory yet.<br/><br/>How does this external change impact the project scope/backlog?

Answer options:

A.

It has no impact as the standard is not mandatory.

B.

New user stories must be added to the backlog and prioritized against existing work.

C.

The project must be paused to rewrite the charter.

D.

The team must work overtime to include the new standard without affecting the schedule.

How to approach this question

External Opportunity -> PO Decision -> Backlog Update.

Full Answer

B.New user stories must be added to the backlog and prioritized against existing work.✓ Correct
External changes can be opportunities. If the PO decides to pursue it, the scope (Backlog) changes. New stories are added and prioritized. Agile teams do not just add work on top (D); they trade off priorities.

Common mistakes

Thinking 'not mandatory' means 'ignore' (A), ignoring the PO's decision.