PMP · Question 28 · Task 2: Evaluate and deliver project benefits and value
A non-profit organization initiates a project to raise awareness about clean water. The primary value is 'Social Impact', which is intangible.<br/><br/>How should the project manager approach the measurement of this value?
Answer options:
Do not measure it, as intangible benefits cannot be tracked.
Identify proxy metrics (e.g., survey responses, website engagement) to quantify the impact.
Convert the social impact into a dollar value using arbitrary estimates.
Focus only on the cost of the campaign.