Hard1 markMultiple Choice
PMP · Question 12 · Task 1: Plan and manage project compliance
A project manager is reviewing the project's risk report. A risk regarding 'Potential non-compliance with new accessibility standards' has a high probability and high impact. <br/><br/>Which response strategy is BEST suited for this compliance risk?
A project manager is reviewing the project's risk report. A risk regarding 'Potential non-compliance with new accessibility standards' has a high probability and high impact. <br/><br/>Which response strategy is BEST suited for this compliance risk?
Answer options:
A.
Accept
B.
Mitigate
C.
Transfer
D.
Exploit
How to approach this question
Match the risk type to the strategy. Compliance risks are threats. High impact threats should be Avoided or Mitigated.
Full Answer
B.Mitigate✓ Correct
Compliance risks are threats. 'Mitigate' is the most common active strategy—taking steps to ensure the standards are met (reducing probability of non-compliance). 'Transfer' (insurance) might cover fines but doesn't fix the compliance failure. 'Avoid' would mean cancelling the project or scope, which might be too extreme unless mitigation fails.
Common mistakes
Thinking you can Transfer compliance liability entirely.
Practice the full PMP Business Environment Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard
Expert