Medium1 markMultiple Choice
PMP · Question 74 · Task 6: Plan and manage schedule
A project manager is leading a team that uses 'Planning Poker'. What is the main benefit of this technique?
A project manager is leading a team that uses 'Planning Poker'. What is the main benefit of this technique?
Answer options:
A.
It generates the most accurate time estimates.
B.
It brings diverse perspectives to the surface and builds consensus on the effort/complexity.
C.
It is faster than expert judgment.
D.
It allows the PM to set the estimates.
How to approach this question
Planning Poker = Consensus/Conversation.
Full Answer
B.It brings diverse perspectives to the surface and builds consensus on the effort/complexity.✓ Correct
Task 6 (Schedule). Planning Poker (Wideband Delphi) is designed to avoid bias (anchoring) and trigger discussion when estimates differ, leading to shared understanding.
Common mistakes
Thinking it's just a game or about speed.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert