Medium1 markMultiple Choice
Task 6: Plan and manage scheduleProcessAgileEstimation

PMP · Question 74 · Task 6: Plan and manage schedule

A project manager is leading a team that uses 'Planning Poker'. What is the main benefit of this technique?

Answer options:

A.

It generates the most accurate time estimates.

B.

It brings diverse perspectives to the surface and builds consensus on the effort/complexity.

C.

It is faster than expert judgment.

D.

It allows the PM to set the estimates.

How to approach this question

Planning Poker = Consensus/Conversation.

Full Answer

B.It brings diverse perspectives to the surface and builds consensus on the effort/complexity.✓ Correct
Task 6 (Schedule). Planning Poker (Wideband Delphi) is designed to avoid bias (anchoring) and trigger discussion when estimates differ, leading to shared understanding.

Common mistakes

Thinking it's just a game or about speed.