    PracticePMI PMP®PMI PMP Practice ExamQuestion 73
    Hard1 markMultiple Choice
    Task 9: Collaborate with stakeholdersPeopleStakeholders

    PMP · Question 73 · Task 9: Collaborate with stakeholders

    A project manager is leading a project to implement a new accounting standard. The CFO is the sponsor. The PM realizes that the CFO has not been attending the steering committee meetings and is delaying key decisions. What should the PM do?

    Answer options:

    A.

    Proceed without the decisions.

    B.

    Complain to the CEO.

    C.

    Schedule a private meeting with the CFO to discuss the impact of the delays and reaffirm their engagement/expectations.

    D.

    Replace the sponsor.

    How to approach this question

    Disengaged Sponsor -> Direct Conversation.

    Full Answer

    C.Schedule a private meeting with the CFO to discuss the impact of the delays and reaffirm their engagement/expectations.✓ Correct
    Task 4 (Engage stakeholders) and Task 9 (Collaborate). Even sponsors need management. The PM must explain the consequences of inaction to get the sponsor back on track.

    Common mistakes

    Being passive or bypassing the sponsor.
    Question 72All questionsQuestion 74

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →