    PracticePMI PMP®PMI PMP Practice ExamQuestion 71
    Medium1 markMultiple Choice
    Task 2: Manage communicationsPeopleCollaboration

    PMP · Question 71 · Task 2: Manage communications

    A project manager is leading a project to develop a new vaccine. The project has high visibility and high risk. The PM sets up a 'War Room' (or 'Obeya'). What is the primary purpose of this?

    Answer options:

    A.

    To isolate the team from the rest of the company.

    B.

    To save money on office space.

    C.

    To enhance communication and collaboration through colocation and information radiators.

    D.

    To monitor the team's attendance.

    How to approach this question

    War Room = Communication.

    Full Answer

    C.To enhance communication and collaboration through colocation and information radiators.✓ Correct
    Task 2 (Communications) and Task 6 (Build a team). Colocation (War Room) is a powerful technique for high-speed communication and problem solving.

    Common mistakes

    Thinking it's about control.
    Question 70All questionsQuestion 72

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →