Medium1 markMultiple Choice
PMP · Question 70 · Task 5: Plan and manage budget and resources
A project manager is reviewing the project resource plan. They notice that a critical expert is over-allocated (booked 150%) in the next month. What technique should the PM use to resolve this?
A project manager is reviewing the project resource plan. They notice that a critical expert is over-allocated (booked 150%) in the next month. What technique should the PM use to resolve this?
Answer options:
A.
Resource Smoothing
B.
Resource Leveling
C.
Crashing
D.
Fast Tracking
How to approach this question
Over-allocation -> Leveling.
Full Answer
B.Resource Leveling✓ Correct
Task 5 (Resources). Resource Leveling is the technique to resolve over-allocation constraints, usually by delaying tasks.
Common mistakes
Confusing Smoothing (optimizing within time limits) with Leveling (resolving constraints, potentially changing time).
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard