PMP · Question 67 · Task 3: Assess and manage risks
A project manager is using a 'Risk Burndown Chart'. What is this tool tracking?
Answer options:
The number of risks identified.
The cumulative severity (probability * impact) of open risks over time.
The money spent on risk responses.
The number of issues.