For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice ExamQuestion 67
    Hard1 markMultiple Choice
    Task 3: Assess and manage risksProcessRiskTools

    PMP · Question 67 · Task 3: Assess and manage risks

    A project manager is using a 'Risk Burndown Chart'. What is this tool tracking?

    Answer options:

    A.

    The number of risks identified.

    B.

    The cumulative severity (probability * impact) of open risks over time.

    C.

    The money spent on risk responses.

    D.

    The number of issues.

    How to approach this question

    Burndown = Remaining. Risk Burndown = Remaining Risk Exposure.

    Full Answer

    B.The cumulative severity (probability * impact) of open risks over time.✓ Correct
    Task 3 (Risk). A Risk Burndown chart visualizes the effectiveness of risk management efforts. The line should go down as risks are mitigated or expire.

    Common mistakes

    Thinking it just counts the number of risks (a low severity risk is not equal to a high severity one).
    Question 66All questionsQuestion 68

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →