    PracticePMI PMP®PMI PMP Practice ExamQuestion 66
    Hard1 markMultiple Choice
    Task 10: Manage project changesProcessChange Management

    PMP · Question 66 · Task 10: Manage project changes

    A project manager is leading a project to launch a new website. The marketing team wants to change the color scheme one week before launch. This is a cosmetic change but requires significant rework. What should the PM do?

    Answer options:

    A.

    Do it to keep the client happy.

    B.

    Reject it immediately.

    C.

    Assess the impact on the launch date and cost, then present the trade-offs to the marketing team (e.g., 'We can do it, but launch will be delayed by 3 days').

    D.

    Ask the developers to work overtime.

    How to approach this question

    Late Change -> Impact Analysis -> Stakeholder Decision.

    Full Answer

    C.Assess the impact on the launch date and cost, then present the trade-offs to the marketing team (e.g., 'We can do it, but launch will be delayed by 3 days').✓ Correct
    Task 10 (Changes). The PM's job is to make the consequences of change visible so the business can make an informed decision.

    Common mistakes

    Saying Yes (Pleaser) or No (Blocker) without data.
    Question 65All questionsQuestion 67

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →