Hard1 markMultiple Choice

PMP · Question 56 · Task 11: Plan and manage procurement

A project manager is reviewing the procurement strategy. The project requires a vendor to develop a proprietary algorithm. The IP (Intellectual Property) rights are a critical concern. Which document must clearly define the IP ownership?

Answer options:

A.

Non-Disclosure Agreement (NDA)

B.

The Contract / Agreement (specifically the Terms and Conditions)

C.

Statement of Work (SOW)

D.

Risk Register

How to approach this question

Legal ownership = Contract.

Full Answer

B.The Contract / Agreement (specifically the Terms and Conditions)✓ Correct
Task 11 (Procurement). IP rights are a critical part of project agreements (Task 8). They must be explicit in the contract.

Common mistakes

Thinking NDA covers ownership.