Hard1 markMultiple Choice
PMP · Question 55 · Task 6: Plan and manage schedule
A project manager is leading a project with a team that is new to Agile. The team is struggling to estimate stories using Story Points. They keep trying to equate points to hours. What should the PM do?
A project manager is leading a project with a team that is new to Agile. The team is struggling to estimate stories using Story Points. They keep trying to equate points to hours. What should the PM do?
Answer options:
A.
Let them use hours since it's easier for them.
B.
Create a conversion table: 1 point = 4 hours.
C.
Facilitate an exercise using 'Affinity Estimation' (grouping items by size) to help them understand relative sizing without numbers first.
D.
Estimate the points for them.
How to approach this question
Coaching (Task 13/5). Move from Absolute to Relative estimation.
Full Answer
C.Facilitate an exercise using 'Affinity Estimation' (grouping items by size) to help them understand relative sizing without numbers first.✓ Correct
Task 6 (Schedule) and Task 13 (Methodology). Relative estimation is a key agile concept. The PM coaches the team to compare items (T-shirt sizing/Affinity) rather than predict time.
Common mistakes
Mapping points to hours (B).
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert