    PracticePMI PMP®PMI PMP Practice ExamQuestion 42
    Hard1 markMultiple Choice
    Task 1: Manage conflictPeopleConflictResources

    PMP · Question 42 · Task 1: Manage conflict

    A project manager is leading a cross-functional team. A functional manager complains that one of the team members is spending too much time on the project and neglecting their operational duties. The project charter states the team member is 50% allocated to the project. What should the PM do?

    Answer options:

    A.

    Tell the team member to ignore the functional manager.

    B.

    Show the functional manager the charter and insist on the 50%.

    C.

    Review the team member's actual hours and workload with the team member, then meet with the functional manager to resolve the conflict based on data.

    D.

    Reduce the team member's project tasks immediately.

    How to approach this question

    Conflict Resolution: Gather Data -> Discuss -> Negotiate.

    Full Answer

    C.Review the team member's actual hours and workload with the team member, then meet with the functional manager to resolve the conflict based on data.✓ Correct
    Task 1 (Conflict) and Task 5 (Resources). In a matrix, resource disputes are common. The PM must verify compliance with the resource agreement (Charter) and negotiate a solution.

    Common mistakes

    Being aggressive with the Charter (B) without checking reality.
    Question 41All questionsQuestion 43

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →