Hard1 markMultiple Choice
PMP · Question 41 · Task 8: Plan and manage scope
A project manager is working on a project with a fixed deadline. The team realizes they cannot complete all the scope by the deadline. The sponsor says the deadline is immovable, but some features are less important. Which approach should the PM use?
A project manager is working on a project with a fixed deadline. The team realizes they cannot complete all the scope by the deadline. The sponsor says the deadline is immovable, but some features are less important. Which approach should the PM use?
Answer options:
A.
Crashing the schedule by adding more resources.
B.
Prioritize the backlog (MoSCoW) and descoping the low-priority features.
C.
Fast-tracking the schedule by running tasks in parallel.
D.
Extend the deadline.
How to approach this question
Identify the constraints. Time = Fixed. Scope = Flexible. Action = Cut Scope.
Full Answer
B.Prioritize the backlog (MoSCoW) and descoping the low-priority features.✓ Correct
Task 8 (Manage scope). In fixed-date projects (like Agile), scope is the variable constraint. Prioritization ensures value is delivered even if full scope isn't.
Common mistakes
Trying to force the work (Crashing/Fast-tracking) when the sponsor has already offered scope flexibility.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert