Hard1 markMultiple Choice
Task 1: Plan and manage project complianceBusiness EnvironmentComplianceBudget

PMP · Question 35 · Task 1: Plan and manage project compliance

A project manager is leading a project with a fixed budget. A key stakeholder demands a change that is critical for compliance but will cause a budget overrun. What should the project manager do?

Answer options:

A.

Reject the change due to the fixed budget.

B.

Implement the change and hope to save money elsewhere.

C.

Analyze the impact and submit a change request to the governance board requesting additional funds or scope reduction elsewhere.

D.

Use the management reserve without informing the sponsor.

How to approach this question

Compliance = Mandatory. Budget = Constraint. Solution = Governance/Trade-off.

Full Answer

C.Analyze the impact and submit a change request to the governance board requesting additional funds or scope reduction elsewhere.✓ Correct
Task 1 (Compliance) + Task 5 (Budget). When constraints collide, governance (Task 14) is the resolution path.

Common mistakes

Rejecting compliance (A) or spending unauthorized money (D).