Hard1 markMultiple Choice
PMP · Question 34 · Task 12: Manage project artifacts
A project manager is using a burnup chart to track progress. The 'Total Scope' line has recently jumped up significantly, while the 'Completed Work' line is rising steadily. What does this indicate?
A project manager is using a burnup chart to track progress. The 'Total Scope' line has recently jumped up significantly, while the 'Completed Work' line is rising steadily. What does this indicate?
Answer options:
A.
The team's velocity has increased.
B.
New requirements have been added to the project (Scope Creep or Change).
C.
The project is ahead of schedule.
D.
The team is finding fewer defects.
How to approach this question
Interpret the Chart. Scope Line goes up = More work added.
Full Answer
B.New requirements have been added to the project (Scope Creep or Change).✓ Correct
Task 12 (Manage artifacts). Burnup charts show Scope vs. Progress. If the Scope line rises, work was added. This helps visualize scope creep.
Common mistakes
Confusing Burndown (one line) with Burnup (two lines).
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert