Hard1 markMultiple Choice
PMP · Question 14 · Task 2: Evaluate and deliver project benefits
A project manager is creating a project charter for a new internal initiative. The sponsor provides a high-level budget but no details on the benefits. What should the project manager do?
A project manager is creating a project charter for a new internal initiative. The sponsor provides a high-level budget but no details on the benefits. What should the project manager do?
Answer options:
A.
Proceed with the charter using the budget provided; benefits will be defined during planning.
B.
Work with the sponsor and stakeholders to define and document the high-level project benefits and success criteria before finalizing the charter.
C.
Refuse to sign the charter until a full business case is provided.
D.
Use industry standard benefits for similar projects as placeholders.
How to approach this question
The Charter requires a Business Case/Benefits. If missing, the PM facilitates their definition.
Full Answer
B.Work with the sponsor and stakeholders to define and document the high-level project benefits and success criteria before finalizing the charter.✓ Correct
Task 2 in Business Environment is 'Evaluate and deliver project benefits'. This starts at initiation. The PM collaborates to ensure alignment.
Common mistakes
Thinking the PM just accepts what is given (Order Taker) vs. facilitating clarity (Leader).
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert