PMP · Question 12 · Task 3: Evaluate external business environment changes
A project manager is leading a large transformation project. A new government regulation is announced that will impact the project's compliance requirements in six months. What should the project manager do FIRST?
Answer options:
Immediately implement changes to the project scope to comply with the new regulation.
Analyze the impact of the new regulation on the project's scope, schedule, and cost.
Submit a change request to the Change Control Board (CCB).
Inform the sponsor that the project will be delayed.