    PracticePMI PMP®PMI PMP Practice ExamQuestion 12
    Hard1 markMultiple Choice
    Task 3: Evaluate external business environment changesBusiness EnvironmentExternal Changes

    PMP · Question 12 · Task 3: Evaluate external business environment changes

    A project manager is leading a large transformation project. A new government regulation is announced that will impact the project's compliance requirements in six months. What should the project manager do FIRST?

    Answer options:

    A.

    Immediately implement changes to the project scope to comply with the new regulation.

    B.

    Analyze the impact of the new regulation on the project's scope, schedule, and cost.

    C.

    Submit a change request to the Change Control Board (CCB).

    D.

    Inform the sponsor that the project will be delayed.

    How to approach this question

    Follow the sequence: Event -> Analyze Impact -> Create Change Request -> Approval -> Implement.

    Full Answer

    B.Analyze the impact of the new regulation on the project's scope, schedule, and cost.✓ Correct
    Changes in the business environment (Task 3) require an impact analysis before any action is taken.

    Common mistakes

    Skipping the analysis step and jumping to solutions or change requests.
    Question 11All questionsQuestion 13

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →