PMP · Question 102 · Task 13: Determine appropriate project methodology
A project manager is leading a project to develop a new software application. The team is using Scrum. The PM wants to ensure that the team is constantly improving. Which event is designed for this?
Answer options:
Daily Standup
Sprint Review
Sprint Retrospective
Backlog Refinement