PMP · Question 101 · Task 5: Plan and manage budget and resources
A project manager is leading a project to build a new bridge. The project is using a predictive lifecycle. The PM wants to ensure that the project is on budget. The PM calculates the To Complete Performance Index (TCPI). The TCPI is 1.2. What does this mean?
Answer options:
The project can continue at the current efficiency.
The project team must perform 20% more efficiently than planned for the remaining work to stay within budget.
The project has extra money.
The project is ahead of schedule.
114 questions · hints · full answers · grading