    Task 15: Manage project issuesissue managementvendor discontinuationsecurity risksstakeholder collaboration

    PMP · Question 99 · Task 15: Manage project issues

    A project manager identifies that a previously managed risk has materialized: a key technology vendor has announced they will discontinue support for a critical software component in twelve months, and will stop providing security updates in six months. This affects core system functionality and creates security vulnerabilities. What should the project manager do FIRST?

    Answer options:

    A.

    Update the risk register to reflect that the risk has become a critical issue

    B.

    Begin immediately searching for alternative software components to replace the discontinued one

    C.

    Assess the immediate security implications and long-term functionality impact, then collaborate with stakeholders to determine the optimal response strategy

    D.

    Implement the pre-planned risk response that was developed when this vendor discontinuation risk was first identified

    How to approach this question

    Look for systematic approaches that assess both immediate security risks and long-term impacts, involving stakeholders in determining the best response strategy given timeline constraints.

    Full Answer

    C.Assess the immediate security implications and long-term functionality impact, then collaborate with stakeholders to determine the optimal response strategy✓ Correct
    When risks become issues with both immediate security implications and long-term functionality impact, effective management requires comprehensive assessment and stakeholder collaboration to determine optimal response strategies within the given timeline constraints.

    Common mistakes

    Jumping to predetermined solutions without assessing current security and functionality impact, focusing on documentation before addressing immediate security risks, or not considering both short-term security and long-term functionality implications.
    Question 98All questionsQuestion 100

    Practice the full PMI PMP Practice Exam 6

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has stable re...HardQ03A team member who was previously a high performer has shown declining work quality and missed sev...HardQ04An experienced team member approaches the project manager asking for more autonomy in making tech...HardQ05A project team is transitioning from waterfall to agile methodology. Several team members express...Hard
    View all 100 questions →