    PracticePMI PMP®PMI PMP Practice Exam 6Question 92
    Hard1 markMultiple Choice
    Task 8: Plan and manage scopescope managementsustainable pacecustomer feedbackcapacity management

    PMP · Question 92 · Task 8: Plan and manage scope

    During sprint planning, the product owner presents several new high-priority user stories that emerged from recent customer feedback. The development team expresses concern that adding these stories will impact their ability to complete previously committed work and maintain sustainable pace. What should the project manager do FIRST?

    Answer options:

    A.

    Add the new stories to the sprint since they represent important customer feedback and are high priority

    B.

    Reject the new stories since they weren't in the original sprint planning and would disrupt commitments

    C.

    Facilitate a discussion about team capacity, business priorities, and sustainable approaches to managing the new requirements

    D.

    Ask the team to work additional hours to accommodate both the original commitments and new high-priority work

    How to approach this question

    Look for collaborative approaches that balance business needs with team capacity and sustainable agile practices rather than compromising team sustainability.

    Full Answer

    C.Facilitate a discussion about team capacity, business priorities, and sustainable approaches to managing the new requirements✓ Correct
    Effective scope management in agile requires facilitating discussions about capacity, priorities, and sustainable approaches rather than simply accepting changes that compromise team sustainability or rejecting valuable customer feedback.

    Common mistakes

    Automatically accepting high-priority requests without considering sustainability, rigidly rejecting changes without exploring options, or compromising team sustainability for short-term gains.
    Question 91All questionsQuestion 93

    Practice the full PMI PMP Practice Exam 6

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has stable re...HardQ03A team member who was previously a high performer has shown declining work quality and missed sev...HardQ04An experienced team member approaches the project manager asking for more autonomy in making tech...HardQ05A project team is transitioning from waterfall to agile methodology. Several team members express...Hard