Hard1 markMultiple Choice
Task 3: Assess and manage riskstechnical riskauthentication servicesspike testingagile risk management

PMP · Question 87 · Task 3: Assess and manage risks

During iteration planning, the team identifies a new technical risk: the third-party authentication service they planned to integrate may not handle the expected user load during peak usage periods, potentially causing system failures. This could impact the upcoming release. What should the project manager do FIRST?

Answer options:

A.

Add the risk to the risk register and schedule detailed analysis and planning for the next iteration

B.

Remove the authentication service integration from the current iteration to avoid the risk entirely

C.

Conduct a technical spike to test the authentication service's capacity limits and identify potential solutions or alternatives

D.

Escalate the risk to the product owner for a scope and priority decision

How to approach this question

Look for approaches that provide quick technical risk assessment and solution exploration, especially in agile contexts where rapid feedback and testing are valuable.

Full Answer

C.Conduct a technical spike to test the authentication service's capacity limits and identify potential solutions or alternatives✓ Correct
In agile environments, conducting technical spikes to quickly assess technical risks through testing and explore solutions provides the rapid feedback needed for informed decision-making about technical integration risks.

Common mistakes

Delaying technical risk assessment, making premature scope decisions without technical information, or escalating without sufficient technical analysis and solution exploration.

Practice the full PMI PMP Practice Exam 6

100 questions · hints · full answers · grading

More questions from this exam