PMP · Question 59 · Task 10: Manage project changes
A key stakeholder requests a significant feature addition during the execution phase of a predictive project. The change would add substantial business value but would impact the timeline by 6 weeks and increase the budget by 15%. What should the project manager do FIRST?
Answer options:
Implement the change immediately since it adds substantial business value
Reject the change to protect the project baseline and committed timeline
Conduct a comprehensive impact assessment on scope, schedule, cost, quality, and risk, then submit to change control board
Negotiate with the stakeholder to implement a reduced version of the feature
100 questions · hints · full answers · grading