PMP · Question 55 · Task 6: Plan and manage schedule
A project manager is developing a schedule for a software project with the following activities on the critical path: Analysis (5 days), Design (8 days), Development (12 days), Testing (6 days), and Deployment (2 days). If Development can be started 3 days after Design begins (fast-tracking), what is the new critical path duration?
Answer options:
30 days
28 days
27 days
25 days
100 questions · hints · full answers · grading