Hard1 markMultiple Choice
Task 4: Engage stakeholdersstakeholder analysisstakeholder categorizationengagement strategiespower-interest analysis

PMP · Question 53 · Task 4: Engage stakeholders

A project manager is analyzing stakeholders for a new enterprise software implementation. The analysis reveals diverse stakeholder groups including end users, IT operations, compliance officers, and executive sponsors, each with different levels of influence and interest. What should the project manager do FIRST?

Answer options:

A.

Create a comprehensive communication plan that treats all stakeholders equally

B.

Categorize stakeholders based on their power, interest, and influence levels to develop tailored engagement strategies

C.

Focus engagement efforts primarily on the executive sponsors since they have the most power

D.

Schedule regular meetings with all stakeholder groups to ensure consistent communication

How to approach this question

Look for systematic approaches that recognize stakeholder differences and develop appropriate engagement strategies for each category.

Full Answer

B.Categorize stakeholders based on their power, interest, and influence levels to develop tailored engagement strategies✓ Correct
Effective stakeholder engagement requires systematic categorization of stakeholders followed by development of tailored engagement strategies appropriate for each group's power, interest, and influence levels.

Common mistakes

Using one-size-fits-all approaches, focusing only on high-power stakeholders, or not recognizing the need for different engagement strategies.