PMP · Question 45 · Task 10: Build shared understanding
During a project planning session, the development team and business analysts have different interpretations of a key requirement, leading to confusion about project scope and deliverables. The disagreement is causing delays in planning. What should the project manager do FIRST?
Answer options:
Make a decision about the requirement interpretation to keep the project moving forward
Facilitate a workshop with both groups to explore the root cause of the different interpretations
Ask the business sponsor to provide clarification on the requirement for both teams
Document both interpretations and proceed with parallel development approaches