    PracticePMI PMP®PMI PMP Practice Exam 5Question 60
    Hard1 markMultiple Choice
    Task 9: Integrate project planning activitiesproject integrationdependency analysisworkstream coordinationintegration planning

    PMP · Question 60 · Task 9: Integrate project planning activities

    A project manager is integrating plans from multiple workstreams for a large organizational transformation project. During integration analysis, they discover that the training plan assumes all system changes will be completed before training begins, but the system implementation plan shows a phased rollout over six months. This creates a significant integration gap. What should the project manager do FIRST?

    Answer options:

    A.

    Modify the training plan to align with the phased system implementation approach

    B.

    Analyze all workstream dependencies to understand the full impact of the integration gap on project objectives

    C.

    Change the system implementation to complete all changes before training begins

    D.

    Schedule a meeting with both workstream leads to negotiate a compromise solution

    How to approach this question

    When integration gaps are discovered, analyze all dependencies and impacts before making changes to ensure solutions optimize overall project outcomes.

    Full Answer

    B.Analyze all workstream dependencies to understand the full impact of the integration gap on project objectives✓ Correct
    Project integration requires understanding all workstream dependencies and their impacts on project objectives before making changes. This prevents solutions that fix one issue but create others.

    Common mistakes

    Students often choose immediate workstream modifications (A or C) or bilateral negotiation (D), missing the need for comprehensive dependency analysis first.
    Question 59All questionsQuestion 61

    Practice the full PMI PMP Practice Exam 5

    94 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn over the past t...HardQ04During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 94 questions →