For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 5Question 44
    Hard1 markMultiple Choice
    Task 7: Address and remove impediments, obstacles, and blockers for the teamimpediment removalservant leadershipstakeholder collaborationagile methodology

    PMP · Question 44 · Task 7: Address and remove impediments, obstacles, and blockers for the team

    During a sprint planning meeting, the development team identifies that they cannot complete their planned work because the testing environment is still not available from the infrastructure team. The infrastructure team says they are waiting for security approvals that are taking longer than expected. This is the second sprint affected by this impediment. What should the project manager do FIRST?

    Answer options:

    A.

    Escalate the security approval delay to senior management for expedited processing

    B.

    Ask the development team to work on other user stories that don't require the testing environment

    C.

    Work with the infrastructure and security teams to explore alternative solutions or expedite the approval process

    D.

    Adjust the sprint goal to accommodate the testing environment delay

    How to approach this question

    When impediments persist, servant leaders actively collaborate with stakeholders to find solutions rather than implementing workarounds or escalating immediately.

    Full Answer

    C.Work with the infrastructure and security teams to explore alternative solutions or expedite the approval process✓ Correct
    Servant leaders prioritize removing impediments for their teams through active collaboration with stakeholders to find solutions, whether through alternatives or process improvements.

    Common mistakes

    Students often choose workarounds (B) or escalation (A), missing the servant leader's responsibility to actively work on impediment removal through direct collaboration.
    Question 43All questionsQuestion 45

    Practice the full PMI PMP Practice Exam 5

    94 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn over the past t...HardQ04During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 94 questions →