PMP · Question 25 · Task 9: Integrate project planning activities
A project manager is integrating plans from multiple workstreams including development, testing, infrastructure, and training. During the integration analysis, they discover that the testing plan assumes a 2-week testing period, but the development plan shows features being delivered throughout the final month. This creates a dependency gap that could impact the go-live date. What should the project manager do FIRST?
A project manager is integrating plans from multiple workstreams including development, testing, infrastructure, and training. During the integration analysis, they discover that the testing plan assumes a 2-week testing period, but the development plan shows features being delivered throughout the final month. This creates a dependency gap that could impact the go-live date. What should the project manager do FIRST?
Answer options:
Extend the testing period to accommodate the development delivery schedule
Analyze the dependency relationships and assess the impact on the overall project timeline
Ask the development team to accelerate their delivery to complete before testing begins
Implement parallel testing and development to reduce the overall timeline
How to approach this question
Full Answer
Common mistakes
Practice the full PMI PMP Practice Exam 5
94 questions · hints · full answers · grading
Expert